Many companies have only one universally applicable BOM structure for all areas of their company. This structure usually takes the form of complete single-level BOMs, created in the design department, and used in both material management and the assembly workshop.
The standard SAP system allows you to maintain individual BOMs for any area of your company. These BOMs are maintained independently of each other and are assigned different internal BOM numbers.
Read more…
Viewed 1393 times by 426 viewers
admin Production Planning Module Basic Data, BOMs, SAP PP
The change master record determines which effectivity conditions apply when a BOM is changed. You can either create a change master record with date effectivity (Valid-from date) or with parameter effectivity.
If you want to use company-specific criteria (instead of dates) to determine when changes are effective, parameters to define effectivity can be used then.
Read more…
Viewed 1389 times by 414 viewers
admin Production Planning Module Basic Data, BOMs, SAP PP
The area of validity (plant or group) that was defined when a BOM was created, can be extended. To do this, you allocate the same bill of material to a material in different plants.
- You can allocate a BOM created in a specific plant (such as 0001) to additional plants (such as 0002 and 0003) or to the entire group (blank).
- You can allocate a group BOM to individual plants.
These related BOMs are identified by a common internal BOM number in the standard SAP system. This internal BOM number is displayed on all screens for plant allocations.
Read more…
Viewed 1352 times by 397 viewers
admin Production Planning Module BOMs, SAP PP
In the standard SAP system, validity areas and periods are used to define the precise conditions under which a bill of material is valid in different areas of a company.
Material BOMs can be valid on different organizational levels:
A material BOM can be used to manage data that applies directly to production. This is why the area of validity is the plant. The plant is the location where all necessary work-scheduling procedures are organized, such as MRP and creating routings.
Read more…
Viewed 1348 times by 395 viewers
admin Production Planning Module BOMs, SAP PP
Material BOM is a BOM with Reference to a Material
A bill of material that can be create for a material is known as a material BOM in the SAP System.
To create a material master in the SAP System, you can use the following functions:
Material > Create > Immediately
For this material, the SAP system creates a material master immediately, so that you can also create a BOM for it.
Material > Create > Schedule
For this material, the SAP system only generates a change document. This is why BOM cannot be created for the material at first.
Only when you activate the scheduled material does the SAP system create a material master record. Then you can create a BOM for it.
Read more…
Viewed 1420 times by 387 viewers