Incorrect Cost Estimate with BOM

March 11th, 2010

According BOM of some assembly part, material just consume only component part 1ea. However after executing cost estimate (CK11N transaction). The result got that component 2ea.

 

The error might be caused by some value in material master. If assembly material master is updated the component scrap in percent field on MRP4 view. This makes the cost estimate increased.

 

Component scrap in percent value is also used in material requirement planning (MRP) to determine the quantities of component required. When exploding the bill of material (BOM), the SAP system will increase the required quantities of the components by calculated scrap quantity

Viewed 77 times by 47 viewers

admin Production Planning Module , ,

Special View on a BOM – BOMs Usage

March 5th, 2010

If separate BOMs are maintained for a product in different areas of your company, BOM reporting functions can be used to obtain information that is directly relevant to your requirements.

  • design BOM
  • production BOM
  • costing BOM

Read more…

Viewed 1000 times by 339 viewers

admin Production Planning Module , ,

SAP PP : BOM Usage

March 2nd, 2010

Many companies have only one universally applicable BOM structure for all areas of their company. This structure usually takes the form of complete single-level BOMs, created in the design department, and used in both material management and the assembly workshop.

 

The standard SAP system allows you to maintain individual BOMs for any area of your company. These BOMs are maintained independently of each other and are assigned different internal BOM numbers.

Read more…

Viewed 1436 times by 441 viewers

admin Production Planning Module , ,

Effectivity types of BOM

March 1st, 2010

The change master record determines which effectivity conditions apply when a BOM is changed. You can either create a change master record with date effectivity (Valid-from date) or with parameter effectivity.

If you want to use company-specific criteria (instead of dates) to determine when changes are effective, parameters to define effectivity can be used then.

Read more…

Viewed 1432 times by 430 viewers

admin Production Planning Module , ,

Extending the Area of Validity of BOM

March 1st, 2010

The area of validity (plant or group) that was defined when a BOM was created, can be extended. To do this, you allocate the same bill of material to a material in different plants.

  • You can allocate a BOM created in a specific plant (such as 0001) to additional plants (such as 0002 and 0003) or to the entire group (blank).
  • You can allocate a group BOM to individual plants.

 

These related BOMs are identified by a common internal BOM number in the standard SAP system. This internal BOM number is displayed on all screens for plant allocations.